Friday, 17 September 2010

The secrets inside. September 2010


One section of the Oak staircase in the large apartment

Looking into the dining area from the staircase
As the work outside continues the pace inside picks up with important elements like stairs being added and interesting elements such as an alcove for the fire appearing. The majority of internal walls are complete so for the first time bathrooms look like bathrooms and built in wardrobes are more than lines on the floor.
The Chalet design leans away from a traditional Chalet interior which is often dominated by wood usually Pine stained a peculiar shade of orange. Having said that, wood does play a part in the Chalet interior with French Oak being used for stairs, windows and selected doors. Observing the Carpenter hand cut and finish skirting boards to perfection gives a real appreciation of craftsmanship.

Tuesday, 17 August 2010

Windows give the building a face. August 2010

With the arrival of the window frames in August the building starts to develop its own character. The thickness of the original walls means that many of the windows are deeply set which adds interest. The windows, doors and much of the interior are finished in French Oak which will age gracefully. French windows are designed to open inwards which makes cleaning the outside of windows a much easier task!

Tuesday, 20 July 2010

It starts to look like a real building. July 2010


The new roof starts to take shape
As summer continued so did rapid progress. By the third week of July the supporting structure for the roof was complete. Although the original barn had an effective roof the whole structure had to be replaced as many of the supporting beams were rotten. Building a roof in the Alps is no simple task, the weight of snow is considerable so strength is vital. Each roof also has to be equipped with "snow catchers" which are designed to prevent large slabs of snow sliding off the roof when the temperature rises.To improve light inside the building the design incorporated velux roof windows and sun tubes which both required accommodation in the roof without impacting the integrity.

Friday, 2 July 2010

Moving up. July 2010

July arrived and most people were thinking of their summer holidays, the builders however were making the most of good weather and moving up the building almost to roof level. The main walls were completed and signs of interior infrastructure appeared. The vision of the Architect came into reality for the first time as rooms started to be recognisable.
The balcony framework is slotted into place

Almost at roof level the work continues with an alarming lack of safety equipment

Tuesday, 8 June 2010

In a tight spot. June 2010

With the demolition work complete it was time for the building team to become conscious about their weight. As the barn had never been blessed with utilities the intricate job of laying pipework and wiring began. With original walls in some areas 1 metre wide space was at a premium which called for some nimble work.
Once complete the concrete arrived and the barn began to take shape once again.
Working in very tight spots

Concrete arrives

Saturday, 15 May 2010

Things get worse. May 2010

In definitely a case of things getting worse before they get better the construction required a large amount of demolition. Although the barn had beautiful arched ceilings at the ground floor level local planning rules required the creation of a series of garage areas which involved destroying the beautiful stone arches. As with any old building demolition can uncover surprises, luckily our excellent building team took everything in their stride. 
The walls come down